Redland Reserve Targets 2027, but Reports Differ on 524 vs. 582 Homes

Bluenest’s approved Redland project is targeting a September 2027 start, but a recent update says 524 homes while its own project file lists 582. County records show why the final cap and infrastructure conditions matter.

Investment Danny Penagos 7 min read

Redland Reserve, Bluenest Development’s planned residential community south of SW 272nd Street between Krome Avenue and SW 172nd Avenue, is being positioned for a September 2027 construction start. But current public reporting does not agree on the size of the project: Groundbreak’s October 20 update calls it a 524-unit community, while the same page’s project file lists 582 units. A September 12 Groundbreak report also described 582 homes and 116 workforce-affordable units. The 58-unit difference is not explained in the material reviewed.

That discrepancy matters because the County’s 2025 land-use and zoning approvals established a development framework, density conditions and a proffered housing commitment—not a final construction schedule or a currently marketed unit mix. The public record also shows that infrastructure, school-capacity and environmental questions were part of the review.

The former Redland Farm Life School, a 1916 community landmark photographed in 2020. This is regional context, not a photograph of Redland Reserve. Photo: Jhw57 / Wikimedia Commons, CC BY-SA 4.0.

Where Redland Reserve sits—and what the County approved

The project is in the Redland area of unincorporated Miami-Dade County, near Homestead—not inside the City of Homestead. The County’s application record locates the original site south of SW 272nd Street, between SW 177th Avenue (Krome Avenue) and SW 172nd Avenue. The October 2024-cycle application filed by Bluenest at Krome I LLC covered approximately 91.48 gross acres and 83.22 net acres.

The County’s staff recommendation added two abutting parcels totaling approximately 6.17 gross acres, bringing the map-amendment area to roughly 97.65 gross acres and 89.39 net acres. The July 17, 2025 final ordinance adopted the amendment with staff-recommended changes and acceptance of the proffered Declaration of Restrictions. The concurrent zoning case, Z2024000241, was approved under Zoning Resolution Z-32-25.

The County’s April 25, 2025 supplemental staff report contains the acreage, density analysis, infrastructure review and covenant history. The final CDMP legislative record and zoning record for Z-32-25 document the July 17 actions.

The entitlement is more nuanced than a single unit count

The original application sought to change land designated Estate Density Residential—one to 2.5 dwelling units per gross acre—to Low-Medium Density Residential, six to 13 units per gross acre, while expanding the Business and Office portion of the site. County staff recommended a different structure: add the two adjoining parcels, use Low-Density Residential with a One Density Increase overlay (DI-1) on the residential portion, and retain a Business and Office designation on the commercial portion.

Under the staff-recommended DI-1 approach, the residential land could reach six to 13 units per gross acre if the development incorporates the County’s required sound urban-design principles. Without those principles, the underlying Low-Density Residential range would apply—2.5 to six units per gross acre. The County’s analysis calculated a theoretical maximum of 1,054 residential units under the higher-density scenario, but that was a land-use capacity calculation, not the approved project’s promised unit count.

The covenant reduced the practical ceiling

The applicant’s November 22, 2024 proffered covenant initially limited development to 700 homes. A later covenant dated February 21, 2025 reduced that proposed cap to 644 homes. The final July 17 action approved the application with staff-recommended changes and required the applicant to submit a revised, re-executed legally sufficient CDMP and zoning covenant, joinders and opinions of title within 10 days or the application would be deemed withdrawn. The accessible legislative text does not state a later revised numerical cap.

This is why 1,054, 700 and 644 should not be treated as interchangeable figures. The first was a theoretical density maximum in the County analysis; 700 was an earlier covenant limit; 644 was the later proffer described in the staff report. The current project descriptions of 524 and 582 are later reported program figures, and the final site-plan record is needed to reconcile them.

524 or 582? The recent reports do not reconcile

Groundbreak’s October 20 update describes Redland Reserve as a 524-unit workforce-housing community and says the developer is targeting a September 30, 2027 construction start. Yet the project-file panel on that same page lists 582 units and a 2032 completion. Groundbreak’s September 12 report also described a 582-home project and identified 116 workforce-affordable homes.

The 116-home figure is broadly consistent with a 20 percent workforce component in a 582-home program. It would represent a different share if the total were 524. No source reviewed explains whether 524 is a phase, a subset, a revised total, or an editorial error. Tryphe therefore does not present either number as the final approved unit count.

The October 20 project update and September 12 approval report are useful current trade sources, but the unit-count discrepancy should be resolved against the executed covenant and the latest approved site plan.

Workforce housing is a specific recorded commitment

The County’s February 2025 staff report describes a proffered restriction requiring 20 percent of the dwelling units to be designated as for-sale workforce housing for households earning up to 140 percent of Miami-Dade County’s Area Median Income. That is more specific than simply calling the entire community “affordable” or implying that every home will be income-restricted.

The same covenant summary includes commitments concerning public water and sanitary-sewer connections, local-area impact fees, fire-rescue water flow, perimeter-lighting mitigation and notice to future buyers that the property abuts agricultural zoning where lawful farming activity may continue under Florida’s Right to Farm Act. The exact obligations should be read from the final recorded instrument, not inferred from a marketing description.

Krome Avenue in the Homestead Historic Downtown District. The streetscape provides broader South Dade context; it is not the Redland Reserve site. Photo: Ebyabe / Wikimedia Commons, CC BY-SA 3.0.

Infrastructure questions were explicit in the County review

The 2025 staff analysis did not treat the project as a simple density change. Miami-Dade Water and Sewer reported that no sanitary gravity-sewer connection was in close proximity and identified the need for a new pump station with a site measuring approximately 45 by 65 feet. The station was to be shown on the future zoning site plan and deeded to the County’s Water and Sewer Department.

The County’s Environmental Resources staff also called for a Conceptual Stormwater Master Plan to determine whether area drainage infrastructure would be adequate. These were issues identified during the entitlement review; the sources reviewed here do not establish that the pump station or stormwater plan has since been completed.

School capacity was another material concern. Under the 700-unit scenario analyzed in the 2025 report, the project was projected to generate about 455 students: 237 elementary, 115 middle-school and 103 high-school students. The County’s preliminary analysis identified insufficient capacity in the affected service areas at that time, including South Dade Senior. It stated that final school-concurrency and capacity-reservation determinations would occur during final plat approval, site planning or an equivalent review.

The County report also identified tree resources, potential specimen trees, the Florida bonneted bat consultation area and a 1913 structure that met the age threshold for further historic-resource consideration. Those findings do not mean the project was denied; they show why the final civil, environmental and site-plan record matters as much as the headline unit count.

The 2027 date is a target, not a construction milestone

Groundbreak reports site work in the third quarter of 2027 and a construction-start target of September 30, 2027. That is a forward-looking project schedule, not evidence that construction has begun or that all building permits have been issued. The County’s 2025 land-use and zoning actions establish entitlements subject to their conditions; they do not prove that the current 524- or 582-home program is the one that will be built.

Before treating the date as firm, readers should look for the current site plan, final plat, recorded covenant, pump-station and stormwater approvals, school-concurrency determination and building permits. A schedule can move as those items are resolved.

What buyers, neighbors and investors should verify

  • The latest approved site plan and unit schedule, including whether the operative total is 524, 582 or another figure.
  • The final executed and recorded Declaration of Restrictions, including the numerical cap and the 20 percent for-sale workforce-housing requirement.
  • The current zoning resolution and any later modifications to Z-32-25.
  • The location, ownership and construction status of the required public pump station and the approved stormwater strategy.
  • The final school-concurrency analysis, plat conditions, access plan and any environmental or historic-resource conditions.
  • The actual building-permit and construction records before treating September 2027 as a committed start date.

How Redland fits into South Dade

Redland Reserve is a large unincorporated-area project near Homestead, but it is not a City of Homestead development. That distinction matters when reviewing municipal services, zoning authority and the public records that govern the site.

Tryphe’s related coverage includes the Historic Downtown Homestead neighborhood guide and the separate report on the $245.8 million Homestead electric-bus center. Another Princeton-area proposal appears in the Milton Mirage road-closure report; it is not part of Redland Reserve.

Bottom line

Redland Reserve has a real County land-use and zoning approval, a recorded planning history and a reported 2027 construction target. It also has unresolved public-facing unit counts: 524 in the October 20 update and 582 in that page’s project file and the September 12 report. The County’s 2025 record describes a later 644-unit covenant proposal, a 20 percent for-sale workforce-housing commitment and infrastructure conditions that still need to be tracked through the final site-plan and permit stages. Until the executed covenant and current approved site plan are reconciled, neither 524 nor 582 should be marketed as the definitive final count.

Source documents

Miami-Dade County: April 25, 2025 supplemental staff report for CDMP20240015.

Miami-Dade County: final CDMP ordinance and July 17, 2025 legislative history.

Miami-Dade County: Zoning Resolution Z-32-25, application Z2024000241.

Groundbreak: October 20, 2026 Redland Reserve construction update and September 12, 2026 approval report.

WhatsApp
Contact Us